5 questions will be shown from a total of 30 free practice questions to prepare you for the PMP exam. Enjoy!
1 / 5
1. After completion of a project with specific users in various countries, the project manager’s supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
2 / 5
2. Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
3 / 5
3. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?
4 / 5
4. One of a project manager’s team members is continuously improving. This team member has been a role model and mentor to others in the organization. How should the project manager acknowledge this team member’s commitment?
5 / 5
5. A project manager completes a project management plan for a global project due in 12 months. When two team members leave the project, what should the project manager do?
Your score is
The average score is 40%
Practice Again
More IT practice tests CLICK HERE
More IT practice tests
CLICK HERE